Loudoun County cluster
Densest data center market in the world; interconnection queue and rate pressure are active policy issues.
Supply as reported: Grid, PJM
The verdict is NO_GO for the 4,000 MW, all-grid Loudoun County proposal, and that verdict stands. Economics are not the blocker: a 12% IRR clears the 8% floor, payback is under four years against a seven-year ceiling, and net present value is about $18B on roughly $172B of capital spending. The blockers are an environment score of 30 against a 45 floor, emissions of about 11 Mt a year, a grid draw of 1,180% of regional headroom against a 60% grid-load ceiling, and only 9 ha of measured open land against 661 ha needed. None of the searched alternatives was shown to be viable, so changing the supply mix alone does not rescue this scale at this site. At over 12 years to full build-out, approval on these terms would lock in ratepayer, land and carbon exposure long before the returns could be realised.
- Reduce grid draw to within the 60% grid-load ceiling and regional headroom, rather than the proposed 1,180% of headroom, with firm contracted supply before construction.
- Raise the environment score from 30 to at least the 45 floor, cutting emissions materially below 11 Mt per year through a lower-carbon supply mix and verified procurement.
- Assemble and permit the full land requirement beyond the measured 9 ha of open land, toward the 661 ha the facility and its supply need.
- Re-prove economics at the remediated scale and supply mix with at least an 8% IRR and payback within seven years, without relying on rate impacts for other customers.
- Grid interconnection and ratepayer backlash could delay, curtail or politically block a draw that is far beyond regional headroom.
- Land assembly beyond the 9 ha measured on site may fail, fragment, or inflate costs across the 661 ha requirement.
- The 320 gram per kilowatt-hour grid intensity drives about 11 Mt of annual emissions and leaves the environment score well below its floor.
- The 7% annual decay in GPU-hour pricing, a year-five GPU refresh, and 69% utilisation could compress the modelled returns over the long build.
- Local opposition could intensify despite a community score of 70, given a negative sentiment shift and the scale, noise, traffic and water demands in the densest data centre market in the world.
| Supply mix | 50% on-site · 50% solar |
| IT load | 4,000 MW |
| Hardware | B200 · 80 kW racks |
| Crew · automation | 2,500 · 20% |
| Plan scores | 63 · E 56 · Env 64 · C 72 |
| Live in · payback | 149 mo · 4.2 yrs |
| Clears the floors | no |
- Gate 0 — no build: no land close or construction until full land assembly, community agreement, permits and firm supply for the phase are secured, reflecting that measured open land is only 9 ha against 661 ha needed.
- Gate 1 — enabling works: permitting, community agreement and supply procurement proceed in parallel, but civil works start only when the grid-load and environment floors can be met for the capacity to be built.
- Phase 1: first 148 MW hall with B200 racks at 80 kW density, energised only as contracted supply lands and commissioning confirms PUE and noise and traffic compliance.
- Phases 2 to 32: each subsequent 148 MW hall is gated individually on secured land, landed firm supply, community-score monitoring above the 40 floor, and re-proven economics, with a stop right if any gate fails.
- Local-first hiring for construction trades, tied to the 2,000 construction jobs and about 3,600 permanent jobs, with published local employment reporting through a community liaison.
- Published and enforceable noise and traffic limits, with monitoring against the proposal's noise and traffic indices and a funded complaint and remediation process overseen by the liaison.
- Heat-reuse or water-offset agreement with the municipality, with annual public reporting on water use, local spend and tax contributions.
- Ratepayer-protection commitment that no phase energises until its share of firm supply is contracted, so other customers are not exposed to grid shortfalls.
| Mix | Viable | Score | Payback | IRR | CO₂ kt/yr |
|---|---|---|---|---|---|
| Gas + solar 50% on-site · 50% solar | no | 63 | 4.2 yrs | 7% | 7,249 |
| Renewables + SMR 50% small · 30% solar · 20% wind | no | 63 | 4.6 yrs | 6% | 486 |
| Hydro PPA + grid 60% hydro · 40% grid | no | 59 | 3.6 yrs | 12% | 4,820 |
| SMR long-term 70% small · 30% grid | no | 58 | 3.8 yrs | 10% | 3,612 |
| As proposed (100% grid) 100% grid | no | 55 | 3.5 yrs | 12% | 11,188 |
| Solar + wind + grid backup 40% solar · 30% grid · 30% wind | no | 55 | 4.7 yrs | 5% | 3,463 |
| Grid + solar 60% grid · 40% solar | no | 54 | 4.1 yrs | 8% | 6,690 |
| Grid + wind 60% grid · 40% wind | no | 54 | 4.1 yrs | 8% | 6,482 |
| Gas bridge 70% on-site · 30% grid | no | 53 | 3.4 yrs | 13% | 13,595 |
Energy what-if
| Metric | This mix | Baseline |
|---|---|---|
| Build cost | $172.1B | $172.1B |
| Months to live | 149 | 149 |
| Blended power | $0.082/kWh | $0.082/kWh |
| Utilization | 69% | 69% |
| EBITDA / yr | $49.6B | $49.6B |
| Payback | 3.5 yrs | 3.5 yrs |
| IRR | 12.4% | 12.4% |
| CO₂ / yr | 11,188,222 t | 11,188,222 t |
| Carbon intensity | 320 g/kWh | 320 g/kWh |
| Water / yr | 83,957,746 m³ | 83,957,746 m³ |
| Grid draw vs headroom | 1180% | 1180% |
| Land | 661 ha | 661 ha |
| Permanent jobs | 3,635 | 3,635 |
| Nuisance index | 50 | 50 |
- Measured open land is 9 ha; the facility and its supply need 661 ha, so land must be assembled beyond the site (sam-3.1).
- Grid draw is 1180% of regional headroom; rate impacts for other customers are likely.
Region profile country priors
| Industrial power | $0.082/kWh |
| Grid carbon | 320 g/kWh |
| Interconnect lead | 30 months |
| Grid headroom | 400 MW |
| Grid reliability | 96% |
| Construction trades | 15,000 @ $48/h |
| Land index | 3.20× |
| Sentiment | 38 / 100 |
| Climate · water | temperate · low stress |
| Solar · wind | 0.60 · 0.40 |
| Geothermal · flare gas | no · yes |
| People within 5 km | unknown |
Baseline build cost
Scenarios
| Name | Mix | Score | Payback | Verdict | |
|---|---|---|---|---|---|
| Baseline as reportedbaseline | 100% grid | 55 | 3.5 yrs | No go |