AI Infrastructure SimCity
Register a site
Executive view

Portfolio and pipeline

Baseline estimates for every tracked site under its reported supply mix. Push the crew, automation and hardware decisions across the whole portfolio and watch schedule, capex and payback move. Conditions come from the advisor's latest verdicts.

Pipeline capex
$620.1B
17 sites not yet operational
Portfolio EBITDA / yr
$283.1B
Compute at build-out
36,467 PF
Median payback
3.6 yrs
Median time to live
46 mo
pipeline
Capex by country
Open conditions
  • Black Sea AI Gigafactory
    • Switch the supply from the proposed 50% grid and 50% nuclear mix to the only viable alternative shown, 50% gas and 50% solar, which lifts the environment score above the 45-point floor and removes dependence on grid headroom.
    • Assemble and permit the land required for the facility and its solar supply beyond the 10 ha measured open at Cernavoda, with the full footprint secured before major construction starts.
    • Contract firm gas and solar supply, water for cooling make-up, and grid backup arrangements so utilization and power costs hold close to the modelled levels.
  • Applied Digital AI Factory campus
    • Contract the viable SMR long-term supply — 70% nuclear and 30% grid — before land close, and cap grid draw at that share so grid load stays at 59%, below the 60% floor.
    • Gate each of the six phases on firm power actually delivered, not on hall completion, so racks are only energized as nuclear and grid supply lands.
    • Secure cooling make-up and municipal agreements tied to the surface water 309 metres from the site, plus published noise and traffic limits, before construction starts.
  • Western Sydney campus
    • Replace the proposed 65% grid and 35% solar mix with the viable Hydro PPA plus grid mix of 60% hydro and 40% grid, lifting the environment score from 33 to 51, above the 45 floor, and cutting emissions from 937 kt a year to 607 kt a year.
    • Confirm the reduced grid draw stays at or below the 60% regional headroom floor, down from 61% as proposed, with a firm interconnection and rate-impact agreement before financial close.
    • Secure a contracted municipal or well cooling water supply before construction, since no surface water was measured within proximity of the site, and confirm land control for the full facility and supply footprint beyond the 69 ha of measured open land.
  • Sines campus
    • Adopt a viable zero-grid energy mix instead of the proposed 35% grid mix, which draws 99% of regional headroom against a 60% floor.
    • Assemble and secure the roughly 1,410 hectares needed for the facility and its gas and solar supply, beyond the 7 hectares of measured open land at the site.
    • Lock in firm gas and solar supply, land close, and community commitments before each phase is energized, so utilization and the community score stay above their floors.
  • Hyderabad AI campus
    • Contract the hydro PPA plus grid mix shown viable before land close, so environment rises above the 45 floor and returns clear the 8% IRR floor.
    • Assemble the land beyond the measured site needed for the facility and its supply, with title and access secured before construction starts.
    • Secure a municipal or well cooling-water supply in writing, as no surface water was measured near the site.
  • Humain hyperscale
    • Adopt the viable Hydro PPA + grid mix — 60% hydro and 40% grid — instead of the as-proposed 65% grid and 35% solar mix, lifting the environment score above the 45 floor and bringing grid draw within the 60% maximum grid load share.
    • Assemble the 223 hectares required for the hydro-backed configuration beyond the measured site, where 0 hectares of open land were measured, before land close and financial commitment.
    • Secure a contracted municipal or well water supply for cooling, with a water offset agreement, as no surface water was measured within 1 kilometre of the site and annual use is about 20 million cubic metres.
  • Lordstown Stargate
    • Contract a firm hydro PPA for 60% of supply with 40% grid before land close, lifting the environment score above the 45 floor and cutting emissions to about 744 kt a year.
    • Assemble enough land beyond the 44 ha of measured open land to reach the 79 ha the facility and its supply need, with permitting and a community agreement secured first.
    • Keep grid draw consistent with the 60% maximum grid-load floor, rather than the 94% in the as-proposed case, and confirm rates and headroom with the utility in writing.
  • Doña Ana County Stargate
    • Adopt a viable low-carbon mix shown in the search, such as 50% nuclear, 30% solar and 20% wind, instead of the proposed 65% grid and 35% solar, so environment rises above the 45 floor and grid load falls within the 60% limit.
    • Assemble the land required beyond the 77 hectares measured open at the site, secure a municipal or well water supply for cooling, and confirm that supply in writing before financial close.
    • Lock in the nuclear, solar and wind supply, permits and interconnection or on-site delivery schedule on a timeline that supports the phased build and protects the 8% minimum IRR.
  • Mesa campus
    • A firm Hydro PPA plus grid agreement covering 60% hydro and 40% grid must be executed before land close, lifting environment to 55 and community to 48, both above their floors.
    • Land beyond the 8 ha of measured open land must be assembled to reach the roughly 60 ha this supply configuration needs.
    • A municipal or well water supply and offset agreement must be secured, since no surface water was measured within 0.7 km and Mesa sits in a high-stress, hot basin.
  • Council Bluffs
    • Adopt the viable Hydro PPA + grid mix at 60% hydro and 40% grid instead of the proposed 70% grid and 30% wind, lifting the environment score from 43 to 55, above the 45 floor, and the composite score from 62 to 68.
    • Assemble and secure the full land requirement beyond the 3 ha of measured open land before land close, with the hydro configuration needing 93 ha in total.
    • Contract the hydro PPA and confirm grid capacity for only the reduced grid share before construction, so the project no longer relies on a 77% draw on regional headroom above the 60% floor.
SiteStatusMWCapex ▼Live inCritical pathJobs build / permRevenue / yrEBITDA / yrPaybackIRRVerdict
Loudoun County cluster
Multiple operators · United States
Operational4,720$168.4B149 mo32 construction phases2,000 / 3,635$54.3B$49.6B3.4 yrs13%No go
Project Rainier
Amazon / Anthropic · United States
Operational2,077$72.8B75 mo14 construction phases2,000 / 1,605$23.7B$22.1B3.3 yrs14%Conditional
Hyperion
Meta · United States
Under construction1,888$67.5B70 mo13 construction phases2,000 / 1,460$19.6B$18.4B3.7 yrs11%Go
Black Sea AI Gigafactory
— · Romania
Proposed1,416$55.1B58 mo10 construction phases2,000 / 1,098$15.9B$14.7B3.7 yrs11%Conditional
Humain hyperscale
Humain / PIF · Saudi Arabia
Planned1,596$53.2B60 mo11 construction phases2,000 / 1,098$14.7B$13.8B3.8 yrs10%Conditional
Johor Bahru cluster
Multiple operators · Malaysia
Under construction1,596$53.0B61 mo11 construction phases2,000 / 1,098$14.7B$13.8B3.8 yrs10%No go
Shackelford County Stargate
OpenAI / Oracle / Vantage · United States
Planned1,322$47.0B54 mo9 construction phases2,000 / 1,025$14.3B$13.5B3.5 yrs12%Go
Sines campus
Start Campus · Portugal
Under construction1,133$41.4B49 mo8 construction phases2,000 / 880$11.1B$10.4B4.0 yrs9%Conditional
Hyperscale campus Hesse
Multiple operators · Germany
Operational1,133$40.6B52 mo8 construction phases2,000 / 880$13.3B$11.3B3.6 yrs11%No go
Stargate Abilene
OpenAI / Oracle / Crusoe · United States
Under construction1,133$40.3B49 mo8 construction phases2,000 / 880$12.3B$11.6B3.5 yrs12%Go
Stargate UAE
OpenAI / G42 / Oracle · United Arab Emirates
Under construction1,064$37.7B48 mo8 construction phases2,000 / 735$10.4B$9.8B3.9 yrs10%Go
Doña Ana County Stargate
OpenAI / Oracle · United States
Planned944$34.0B46 mo7 construction phases2,000 / 735$10.0B$9.4B3.6 yrs11%Conditional
Prometheus
Meta · United States
Under construction944$33.2B46 mo7 construction phases2,000 / 735$10.8B$10.0B3.3 yrs14%Conditional
Elsham Tech Park
Elsham Tech Park Limited · United Kingdom
Planned888$33.0B45 mo6 construction phases2,000 / 735$11.0B$9.4B3.5 yrs11%No go
Applied Digital AI Factory campus
Applied Digital · Finland
Proposed888$32.5B42 mo6 construction phases2,000 / 735$11.1B$10.4B3.1 yrs15%Conditional
Fairwater
Microsoft · United States
Under construction850$30.7B42 mo6 construction phases2,000 / 663$8.6B$7.9B3.9 yrs9%Conditional
Dublin cluster
Amazon Web Services · Ireland
Operational710$26.7B46 mopower supply2,000 / 590$8.2B$7.3B3.6 yrs11%No go
Council Bluffs
Google · United States
Operational661$23.6B37 mo5 construction phases2,000 / 518$7.2B$6.7B3.5 yrs12%Conditional
Lordstown Stargate
OpenAI / SoftBank · United States
Planned566$20.0B34 mo4 construction phases2,000 / 445$6.5B$6.0B3.3 yrs14%Conditional
Hyderabad AI campus
Multiple operators · India
Planned532$17.9B32 mo4 construction phases1,920 / 373$4.5B$4.2B4.3 yrs7%Conditional
Quincy campus
Microsoft · United States
Operational472$16.8B33 mo4 construction phases1,920 / 373$5.3B$4.9B3.4 yrs13%Go
Mesa campus
Google · United States
Operational426$14.3B68 mopower supply1,536 / 300$4.0B$3.7B3.9 yrs9%Conditional
Western Sydney campus
Multiple operators · Australia
Under construction378$13.8B31 mo3 construction phases1,536 / 300$4.0B$3.6B3.8 yrs10%Conditional
Colossus
xAI · United States
Operational283$10.0B30 mo2 construction phases1,152 / 228$3.2B$3.0B3.3 yrs14%Conditional
Hamina
Google · Finland
Operational266$9.9B28 mo2 construction phases1,152 / 228$2.9B$2.8B3.6 yrs11%Go
Narvik AI campus
Multiple operators · Norway
Planned266$9.8B29 mo2 construction phases1,152 / 228$3.2B$2.9B3.4 yrs13%No go
Odense
Meta · Denmark
Operational178$6.7B30 mo2 construction phases768 / 155$2.1B$1.9B3.5 yrs12%Go

The sliders apply the same crew, automation and hardware decision to every site and recompute the engine in the browser; the "Live in" delta is against each site's own plan.