Stargate Abilene
Flagship Stargate campus; first buildings energized in 2025 with expansion continuing through 2026.
Supply as reported: Grid interconnect with on-site gas turbines; wind in the ERCOT mix
The verdict is GO because Stargate Abilene clears every floor: 12% IRR against an 8% minimum, payback in about three and a half years against a 7-year maximum, a community score of 73 against a 40 floor, and grid load of 23% against a 60% cap. The environmental case is the constraint, scoring 46 against a 45 floor, with emissions of about 2 Mt a year, so the proposed mix must not drift toward the non-viable higher-carbon alternatives. At about $41B of capex for 960 MW of IT load, 672,000 B200 GPUs and about $4B of ten-year NPV, the economics work if utilization and power pricing hold. Land and water are gating items, not footnotes: only 9 ha of open land was measured against 295 ha needed, and cooling depends on municipal or well supply.
- Assemble land beyond the 9 ha measured open on site to the full 295 ha required for the facility and its supply before full campus close.
- Secure contracted municipal or well water for cooling, with no surface water measured within sight of the site, and keep water use and discharge within agreed municipal limits.
- Hold the environment score at or above the 45 floor — it is estimated at 46 — by keeping the proposed gas, wind and grid mix and controlling carbon intensity and water demand.
- Keep economics above floors, with IRR at or above 8% and payback within 7 years, and keep grid draw within 60% of regional headroom — it is estimated at 23%.
- Confirm power supply, rack and GPU delivery for each 142 MW phase before energizing the next phase.
- Environment is only one point above its floor, so any shift to more gas or grid power, higher carbon intensity or weaker water controls could flip the assessment.
- Land assembly from 9 ha measured open to 295 ha required could delay phases, raise cost or shrink the campus.
- Cooling depends on municipal or well water with no nearby surface water measured, creating supply, permitting and community risk in a medium water-stress setting.
- A 49-month, eight-phase build with a peak crew of 2,500 and a GPU refresh in year five exposes the case to labor, supply-chain and technology-price decay risk.
- Emissions of about 2 Mt a year and a 1,133 MW facility load will draw disclosure, grid and local-impact scrutiny even though grid load is within its cap.
| Supply mix | 55% on-site · 27% wind · 18% grid |
| IT load | 960 MW |
| Hardware | B200 · 80 kW racks |
| Crew · automation | 2,500 · 20% |
| Plan scores | 62 · E 69 · Env 46 · C 73 |
| Live in · payback | 49 mo · 3.5 yrs |
| Clears the floors | yes |
- Permitting, land assembly to 295 ha, water agreement and community agreement before land close.
- On-site gas supply and wind procurement in parallel with civil works, gated by firm power contracts for the first phase.
- Phase 1: first 142 MW facility hall energized, gated by supply landing, rack delivery and commissioning sign-off.
- Phases 2 to 4: successive 142 MW halls staggered about four months apart, each gated by power availability, GPU delivery and prior-phase utilization.
- Phases 5 to 8: remaining 142 MW halls to reach 960 MW of IT load, each gated by grid headroom, water capacity and environmental compliance staying above floor.
- Local-first hiring for construction trades, backed by the estimated 2,000 construction jobs and 880 permanent jobs, with regular reporting to the municipality.
- Heat reuse or water offset agreement with the municipality, addressing cooling demand of about 12 million cubic metres a year and the absence of nearby surface water.
- Published noise and traffic limits with a named community liaison, complaint response times and periodic public reporting against those limits.
- Commit the estimated $182M a year in local spend through local procurement targets and publish progress annually to sustain the community score of 73, well above the 40 floor.
| Mix | Viable | Score | Payback | IRR | CO₂ kt/yr |
|---|---|---|---|---|---|
| Renewables + SMR 50% small · 30% solar · 20% wind | yes | 67 | 4.1 yrs | 8% | 120 |
| Hydro PPA + grid 60% hydro · 40% grid | yes | 65 | 3.4 yrs | 13% | 1,355 |
| SMR long-term 70% small · 30% grid | yes | 65 | 3.7 yrs | 11% | 1,018 |
| As proposed (55% on-site · 27% wind · 18% grid) 55% on-site · 27% wind · 18% grid | yes | 62 | 3.5 yrs | 12% | 2,472 |
| Gas + solar 50% on-site · 50% solar | yes | 62 | 3.9 yrs | 9% | 1,770 |
| Solar + wind + grid backup 40% solar · 30% grid · 30% wind | yes | 62 | 4.0 yrs | 8% | 1,004 |
| Gas bridge 70% on-site · 30% grid | no | 60 | 3.3 yrs | 14% | 3,413 |
| Grid + wind 60% grid · 40% wind | no | 59 | 3.6 yrs | 11% | 1,895 |
| Grid only 100% grid | no | 57 | 3.3 yrs | 14% | 3,189 |
| Grid + solar 60% grid · 40% solar | no | 57 | 3.7 yrs | 10% | 1,917 |
Energy what-if
| Metric | This mix | Baseline |
|---|---|---|
| Build cost | $40.6B | $40.6B |
| Months to live | 49 | 49 |
| Blended power | $0.040/kWh | $0.040/kWh |
| Utilization | 65% | 65% |
| EBITDA / yr | $11.6B | $11.6B |
| Payback | 3.5 yrs | 3.5 yrs |
| IRR | 12.2% | 12.2% |
| CO₂ / yr | 2,472,283 t | 2,472,283 t |
| Carbon intensity | 301 g/kWh | 301 g/kWh |
| Water / yr | 11,778,183 m³ | 11,778,183 m³ |
| Grid draw vs headroom | 23% | 23% |
| Land | 295 ha | 295 ha |
| Permanent jobs | 880 | 880 |
| Nuisance index | 48 | 48 |
- Measured open land is 9 ha; the facility and its supply need 295 ha, so land must be assembled beyond the site (sam-3.1).
- No surface water measured within 0.7 km of the site; cooling water depends on municipal or well supply (sam-3.1).
Region profile country priors
| Industrial power | $0.048/kWh |
| Grid carbon | 380 g/kWh |
| Interconnect lead | 14 months |
| Grid headroom | 900 MW |
| Grid reliability | 96% |
| Construction trades | 9,000 @ $33/h |
| Land index | 1.00× |
| Sentiment | 64 / 100 |
| Climate · water | temperate · medium stress |
| Solar · wind | 0.90 · 0.95 |
| Geothermal · flare gas | no · yes |
| People within 5 km | unknown |
Baseline build cost
Scenarios
| Name | Mix | Score | Payback | Verdict | |
|---|---|---|---|---|---|
| Baseline as reportedbaseline | 55% on-site · 27% wind · 18% grid | 62 | 3.5 yrs | Go |